Roof joists on. Steel beam welded in place above the doors. Tiler coming on Friday.
Building Work – Project 3 – Week 5, Day 3

Roof joists on. Steel beam welded in place above the doors. Tiler coming on Friday.
Latest progress
Scaffolding up. Some of the steel has arrived. Brickie back to finish off tomorrow.
A few delays due to rain and Bank Holiday
Walls starting to go up.